Fourth Floor Construction Begins This Week

The New Saint Joseph Hospital is steadily growing. This week seventy-five percent of the third floor columns are in place and the fourth floor decks are scheduled to start construction on August 31st with the first concrete placement on September 24th. There is a mock-up structure of the exterior walls that is on display at the north end of Marion Street. It provides a glimpse as to what the exterior of the hospital will look like.
The employee parking garage at 18th and Downing will be above ground soon. The first deck pour is scheduled for September 17th. This construction will be relatively quick and the planned opening of the garage is the summer of 2013.
If you’ve not seen the new retention pond and surrounding green space on 20th and Downing you should stop over one day. Most of the landscaping is in place with the remainder being placed in the coming weeks.