February Construction Update

The final phase of the sixth floor is being completed soon and the seventh floor is not far behind

The eighth level, which is the roof and will include the helicopter landing pad, was started on February 15th

The fifth floor started getting the exterior wall panel placement at the beginning of the month

At ground level, the Chapel construction continues with the completion of the grade beam placement and backfill

The overhead mechanical and electrical installation continues on levels one through four

Coming up in March

The construction workforce will reach 1,000 people a day
Steel for the Chapel will being arriving
The crane for the associates parking garage will be removed at the end of the month, with a planned opening for June

 Heritage Project Construction January 2013